Bezos Predictions Scorecard #5: Space, How Far Did the 2024 Moon Promise Slip?

Five Blue Origin and Bezos space claims, checked against 2026 results.

Part 5 of our Bezos scorecard covers space. We checked five claims, from the schedule Blue Origin laid out in 2019 to Bezos’s 2025 forecast for space data centers, against results as of November 12, 2026.

5
Claims graded
~4 yrs
New Glenn first-launch delay
3
New Glenn launches, 2025-26
1
Booster reflight success

Claims vs. results

Most of the schedule claims come from the May 2019 Blue Moon unveiling. The last row is a company goal, and the first rows are Bezos’s own statements and event materials.

WhenClaimResult (as of Nov 2026)Verdict
2019-05Blue Origin: help NASA land on the Moon by 2024, with uncrewed tests in 2023 and 2024 and a crewed landing at the end of 2024As of May 2026 the uncrewed Blue Moon MK1 (“Endurance”) is still in testing, with a landing hoped for later in 2026. NASA’s first landing target is 2028 (Artemis 4)MISS
2019-05First New Glenn launch in 2021Slipped to late 2022, then 2024, and finally flew in January 2025 (after a Jan 13 scrub). About four years lateMISS
2019-05First crewed New Shepard flight in late 2019Flew July 20, 2021 (NS-16, Bezos and three others, 10 min 10 sec, about 105 km). About 1 year 7 months lateMISS
2025-11 to 2026-04 (company)Recover and reuse the New Glenn first stageNov 13, 2025: booster recovered on the second flight. Apr 19, 2026: the same booster flew again and landed. But the second stage underperformed and the satellite (BlueBird 7) was lostHIT
2025-10Bezos: gigawatt-scale space data centers in 10+ years, cost-competitive with Earth within a couple of decadesDeadline not reached. He called near-term “2 to 3 years” claims “a little ambitious”IN PROGRESS
New Glenn, from promise to flight
The first-flight date moved four times
20212019 promisefirst launch2022Pushed toend of year2024Pushed again2025Jan first launchNov booster recovery2026Apr third flightreflight, satellite lost
Delay vs. the promise
Years (promised date to actual date)
Crewed flight (late 2019 to Jul 2021)about 1.6New Glenn (2021 to Jan 2025)about 4
New Glenn flight record
2025-01 to 2026-04
Launches3Booster recoveries2 (NG-2, NG-3)Booster reflights1 (NG-3)Missed target orbit1 (NG-3)
🌙
Blue Moon MK1
Uncrewed test lander. Cleared a NASA vacuum test, now in Florida. A landing is hoped for in late 2026.
🛰️
NASA schedule
Artemis 3 targets late 2027, the first landing is Artemis 4 in 2028. MK1 must first demonstrate fuel transfer and autonomous navigation.
🔧
NG-3 root cause
FAA: a cryogenic leak froze a hydraulic line, causing a thrust anomaly in the second-stage engine. Nine corrective actions. Next flight, NG-4, has no announced date.
Verdict breakdown
5 claims
1/5hitsHIT 1IN PROGRESS 1MISS 3
KEY TAKEAWAYS
1
Every dated promise from 2019 slipped: crewed flight by about 1.6 years, New Glenn by about 4, the 2024 Moon landing by years.
2
The capability promise held up: the first stage was recovered in November 2025 and reflown in April 2026.
3
The reflight also exposed the next weak point: the upper stage failed to place its satellite in orbit.
4
The longest bet, space data centers, cannot be graded until the 2030s.
Bottom line
Blue Origin’s schedules have slipped repeatedly since 2019. The 2024 Moon landing did not happen, and New Glenn and the first crewed flight were years late. But the first stage has now been recovered and reflown, and the next test is the Blue Moon MK1 landing and NG-4.

How we grade

  • HIT: the promised outcome is confirmed
  • PARTIAL: only part of the claim is met
  • MISS: deadline passed without delivery, or the opposite happened
  • IN PROGRESS: the deadline has not arrived yet
  • NOT GRADED: no verified data to grade it
  • Results as of November 12, 2026

Limits

  • The 2019 Moon schedule is Blue Origin’s plan presented at the event, not a personal numeric promise from Bezos.
  • We could not verify the outcome of New Glenn’s very first flight, so it is not used in grading.
  • MK1 and NG-4 status was checked through May 2026 sources. Later changes are not reflected.
  • The 2025 space data center forecast is more than ten years out, so its deadline has not passed.

Sources

Next up: Part 6, physical retail.