Jensen Huang Scorecard ③ The One-Year Roadmap: Blackwell Slipped on a Design Flaw, Rubin Entered Production on Time
Blackwell was promised for late 2024 but a design flaw pushed volume shipments into 2025. Five roadmap promises, through Rubin and Rubin Ultra, checked against what shipped.

At Computex in June 2024 Jensen Huang promised a “one-year rhythm” for GPU architectures: Blackwell Ultra in 2025, Rubin in 2026 and Rubin Ultra in 2027. In March he had said Blackwell would reach partners “later this year.” This post grades five roadmap and shipping promises as of November 14, 2026. Note that Huang resigned as Nvidia CEO on November 12, 2026; this series grades public statements he made while CEO.
Claim vs. what happened
Roadmap promises carry years, so they can be graded. Shipping volumes are not published, so we relied on deployment announcements and earnings remarks.
| When | Claim | Result (as of Nov 2026) | Verdict |
|---|---|---|---|
| Jun 2024 (Computex) | One-year rhythm: Blackwell Ultra 2025, Rubin 2026 (HBM4), Rubin Ultra 2027 | Blackwell Ultra (GB300) was about two-thirds of Blackwell revenue by Q3 FY26. Rubin “in full production” in Aug 2026 and running at five clouds. Deadline: 2025 and 2026 | HIT |
| 2024-03-18 (GTC) | Blackwell available from partners later in 2024 | A design flaw pushed volume to Q1 2025; Huang said it was “100% Nvidia’s fault.” Blackwell revenue $11B in the Jan 2025 quarter | PARTIAL |
| 2025-09-09 | Rubin CPX at end of 2026; $5B of token revenue per $100M invested (50x) | No shipment evidence yet. The 50x figure is Nvidia’s own. Deadline Dec 31, 2026 | IN PROGRESS |
| 2026-07-06 (dispute) | Nvidia says the roadmap is intact after SemiAnalysis reports Rubin Ultra’s Kyber racks slipped to 2028 | Claims conflict. The only item with a specific delay allegation. Deadline 2027 | IN PROGRESS |
| GTC 2026 | Feynman in 2028 | Too early to grade | NOT GRADED |
How we grade
- Hit: it happened within the stated deadline
- Partial: only some conditions were met
- Miss: the deadline passed without confirmation, or the opposite happened
- In progress: the deadline has not arrived yet
- Not graded: no confirmed data, so we do not grade it
- Results as of November 14, 2026
Limits
- Shipment volumes are not disclosed; we used deployment announcements and earnings remarks.
- The Blackwell Ultra share (about two-thirds) comes from a transcript Motley Fool warns may contain errors.
- The exact date of the 2024 Computex keynote (around June 2–3) was not confirmed from a primary source.
- The Rubin Ultra delay report is a secondary source (wccftech); Nvidia’s full statement was not seen.
- Purchase commitments are single-source (Futurum), and Q3 FY27 results due November 17 are not reflected.
Sources
- Maginative: Rubin roadmap at Computex 2024
- Nvidia release: Blackwell platform (Mar 18, 2024)
- Fortune: Blackwell delay report (Aug 3, 2024)
- Fortune: fastest product ramp (Feb 26, 2025)
- StorageNewsletter: Rubin CPX announcement
- Futurum: Nvidia Q2 FY27 note
- Wccftech: Rubin Kyber delay rumors and Nvidia’s response
- Motley Fool: Q3 FY26 earnings call transcript
Next up: AGI and AI capability claims.